Brent's Addition Progress Pictures



Day 1 - Wednesday, July 26, 2006
Top        
Initial work begins
  • Shed move
  • Sewer line move
  • Porch removal
Day 1 - Picture 1
Day 1 - Picture 2
Day 1 - Picture 3
Day 1 - Picture 4
Day 1 - Picture 5

Day 1 - Picture 6
Day 1 - Picture 7
Day 1 - Picture 8
Day 1 - Picture 9





Day 2 - Thursday, July 27, 2006
Top        
Excavation complete with frost footing overdig

Day 2 - Picture 1
Day 2 - Picture 2
Day 2 - Picture 3
Day 2 - Picture 4
Day 2 - Picture 5
Day 2 - Picture 6
Day 2 - Picture 7
Day 2 - Picture 8
Day 2 - Picture 9

Day 2 - Picture 10
Day 2 - Picture 11
Day 2 - Picture 12
Day 2 - Picture 13
Day 2 - Picture 14
Day 2 - Picture 15
Day 2 - Picture 16
Day 2 - Picture 17
Day 2 - Picture 18




Day 3 (of work) - Monday, July 31, 2006
Top        
Concrete work starts!! Day 3 - Footing Pictures

  • Staked out footings and wall placement.
  • Footings will be set tomorrow morning with the City's inspection around noon and the pour shortly afterward.
  • Walls will tentatively be poured Monday, August 7th.
  • The floor will be poured in the following two weeks allowing for plenty of cure time before we start framing on September 8th.

    We also made the decision to go with 6' poured walls and a 4' poured wall on the south end. This saves a lot of money and allows us to set standard windows in the wood frame part of the wall.




    Day 4 - Tuesday, August 1, 2006
    Top        
    Day 4 - Footing Pictures 1
    Day 4 - Footing Pictures 2
    Day 4 - Footing Pictures 3
    Day 4 - Footing Pictures 4
    Day 4 - Footing Pictures 5
    Day 4 - Footing Pictures 6
    Day 4 - Footing Pictures 7
    Day 4 - Footing Pictures 8




    Day 5 - Sunday, August 13, 2006
    Top        
    The first week of August brought three major thunderstorms, so the second week of August was allowing the ground to dry. With another impending storm forecast for Sunday evening, Saturday I purchased a 40x60 tarp, eight 15" anchor stakes, and 200 foot of rope. As soon as I started putting the tarp up, I realized I needed more rope and purchased 300 more feet.

    Using garage hooks I secured the tarp to the house above the basement level and beneath the eaves where the porch was (where water was runnign into the dig). I cut up 2x4 chunks, drilled 1/2 inch holes in them, and placed them atop each of the rebar sticking out of the footings to keep the tarp form ripping on them.

    Day 5 - Tarp Pictures 1
    Day 5 - Tarp Pictures 2
    Day 5 - Tarp Pictures 3
    Day 5 - Tarp Pictures 4
    Day 5 - Tarp Pictures 5
    Day 5 - Tarp Pictures 6

    After 5 1/2 hours I had the tarp up and secure, but decided some props were in order. I made three make-shift posts and clamped them to the ropes that support the tarp to keep them from falling over.

    Day 5 - Under Tarp Pictures 1
    Day 5 - Under Tarp Pictures 2
    Day 5 - Under Tarp Pictures 3
    Day 5 - Under Tarp Pictures 4
    Day 5 - Under Tarp Pictures 5

    After all of that work, we only got a little rain, but it was dry under the tarp.

    Day 5 - Wet Tarp Pictures 1
    Day 5 - Wet Tarp Pictures 2




    Day 6 - Monday, August 14, 2006
    Top        
    Monday morning storm rolls in...

    Day 6 - Storm Pictures 1
    Day 6 - Storm Pictures 2
    Day 6 - Storm Pictures 3
    Day 6 - Storm Pictures 4

    Tuesday I checked with the concrete man, and work was to begin Wednesday morning.




    Day 7 - Wednesday, August 16, 2006
    Top        
    Setting the concrete forms really starts to bring things into focus.

    Day 7 - Setting Forms 01
    Day 7 - Setting Forms 02
    Day 7 - Setting Forms 03
    Day 7 - Setting Forms 04

    Pouring the walls...finally.

    Day 7 - Pouring the Walls 01
    Day 7 - Pouring the Walls 02
    Day 7 - Pouring the Walls 03
    Day 7 - Pouring the Walls 04
    Day 7 - Pouring the Walls 05




    Day 8 - Thursday, August 17, 2006
    Top        
    The excavators get right back on it.

    Day 8 - Completed Walls...not "finished" 01
    Day 8 - Completed Walls...not "finished" 02

    Interesting Development - Saturday, August 19th
    During the pouring of the walls, Mr. Pomeroy (owner of PGL Crook-crete) mumbled something about charging me the same price for 6 and 4 foot walls as he would for 9 foot walls. I knew then that something was amiss. I ran in the house and began looking for the bid, and realized quickly from my notes that the only bid I had from him was verbal. I made a note that he commented that the estimate did not include grading labor, because he was the only person that said anything about it. (NOTE: I found out later PGL always overcharges for grading labor. The guys that did the floor said that the grading - done by Zenk - was better than normal.)

    The original bid was $7645 for 9 foot walls with 3 windows in the walls, a pump truck (~$500) to get the concrete into the taller walls, and a retaining wall under the existing structure (we were going to dig down to keep the upper levels at the same height). In an effort to cut costs, I opted to keep the floor level with the existing basement (no retaining wall) and poured 6 foot walls and one 4 foot wall. Considerably less concrete and about the same amount of form setting, no retaining wall (far less labor), and on top of all of that, I let them use exact form widths to make it easier on them (which we have to make up for in our framing). He mentioned that all I really saved was the cost of the pump truck...

    Saturday, August 19th, I received an invoice for the walls, not including the floor. The invoice was for $4639!!! I was so frustrated that I waited until Monday to call and confront him. After a brief, heated discussion on the phone, he was headed up to sign the lein waiver and get his check. Since I had gotten no written quote, I was not aware that he billed in "phases" so that he doesn't get stuck waiting for someone to finish their work. He then argues that the pump truck and windows were not included in the bid, and that the bid was for 8 foot walls (which he has single form sections for). He thinks that since I saved $880 I should be happy.

    Ironically, all of my other WRITTEN bids are for the same work; all inclusive. After speaking to several other people, I discovered that this is commonplace for PGL to over-charge for arbitrary items when ever possible. It appears that the walls I got, UNfinished (he did not vibrate or beat the forms to release air) should have cost around $2500-$3000. But, since I don't have a written bid (let alone the time to pursue fighting it), I opted not to bother arguing, and paid the man. Tad Pomeroy should be prosecuted for practicing such unscrupulous business tactics. He will never see another dime of my money!




    Day 9 - Friday, September 1, 2006
    Top        
    After a few hours on the phone, I managed to get things back on schedule at the last minute. Craig Zenk rearranged his schedule to get my backfill done so that we could pour Saturday morning. (SPECIAL THANKS to Zenk Excavation!!! They kept me on-schedule more than once!) My target for the floor and walls to be done was September 1st, and we finished it on the 2nd! Everyone tells me how amazing it is to be on-schedule with a construction project, so I am pretty happy with everything so far.

    Day 9 - Backfill 01
    Day 9 - Backfill 02




    Day 10 - Saturday, September 2, 2006
    Top        
    Pouring the floor.

    Day 10 - Pouring the Floor 01
    Day 10 - Pouring the Floor 02
    Day 10 - Pouring the Floor 03
    Day 10 - Pouring the Floor 04
    Day 10 - Pouring the Floor 05

    Menard's also brought the first load of materials - the lumber.

    Day 10 - First Menard's Delivery 01
    Day 10 - First Menard's Delivery 02
    Day 10 - First Menard's Delivery 03




    Day 11 - Thursday, September 7, 2006
    Top        
    Delivery Day.

    Day 11 - 9:00 am CDT - Truss Delivery




    Week 1 of Construction - Friday, September 8 through Friday, September 15, 2006
    Top        
    Week 1 of construction

    Construction begins! Eight days of 10-14 hours of work. We'll be setting trusses tomorrow on the new addition. Pending rain on Sunday, we'll be tearing off the old roof on Monday and setting those trusses Monday afternoon or Tuesday.

    I haven't had time to continue to the theme of the page, so I threw together this slide show of what we've accomplished so far. I'll get it all into the same format as soon as I have time.

    Week 2 of construction




    Roofing
    Top        
    The Roof Job

    Roofing took some time. John was here for the weekend, but I was recovering from being sick all week, and the roofing got rained out before noon with only the west side of the old house shingled. We installed my garage doors and openers since it rained and got cold. I did the other half of the old house on Tuesday night; I was home by 4 and on the roof by 4:15, finishing around 8:15 pm using halogen work lights.

    The following weekend Mark came and helped me finish the roof. In two days we were able to get everything on the addition flashed and shingled with the exception of the ridge vent. I installed the roof vent Monday night "under the lights".
  • Jump to a Day

    Day 1 - Shed move, porch removal, sewer line move
    Day 2 - Excavation complete
    Day 3 - Digging footings
    Day 4 - Footings poured
    Day 5 - Tarp pictures
    Day 6 - Storm
    Day 7 - Setting forms and pouring the walls
    Day 8 - Completed walls
    Day 9 - Backfill
    Day 10 - Pouring the floor and the first material delivery
    Day 11 - Trusses, material handler, and roll off dumpster

    Week 1 - Framing construction begins
    Week 2 - Framing construction nears completion

    Roofing - The roof has shingles!

    Photos with Measurements

    Dig Height
    Back Wall


    Blueprints and Drawings

    Garage and Basement level
    Footings
    Upstairs
    Proposed Cabinet Layout